The County is planning for the future corridor of Ronald
Reagan Boulevard between RM 2243 and I-35, which is expected to be an ultimate
eight-lane controlled-access roadway.
The only portion of the Ronald Reagan Blvd that has
construction funding is within the limits of SH 29 and FM 3405. This portion will look to construct a separate
two-lane road to serve as the southbound frontage road of the ultimate
eight-lane roadway and switch the existing roadway to a northbound only
roadway, with a divided median. More information is available on that
project page. Ultimately, as the county grows and funding is
secured, the remaining roadway will be built, resulting in a controlled access
roadway. This portion of the Ronald Reagan Project is a part of the County’s
Long-Range Transportation Plan and was funded through the voter-approved 2013
Road Bond.
|
|
|
Ronald Reagan Corridor Planning Segment A (RM 2243 and SH 29)
|
Project Limits and Length: 3.7 miles from RM 2243 to SH 29
Status: The engineer, LJA Engineering, is working on planning
for the roadway, which is anticipated to be complete in late 2022.
|
|
|
Ronald Reagan Widening Segment B (SH 29 and north of FM 3405)
|
Project Limits and Length: 7 miles from SH 29 to north of FM
3405
Status: For information
on this segment, please visit the project webpage
here.
|
|
|
Ronald Reagan Corridor Planning Segments C (FM 3405 and
Williams Drive)
|
Project Limits and Length: 3.7 miles from FM 3405 and
Williams Drive
Status: Status: The engineer, Volkert, Inc., is working on planning
for the roadway, which is anticipated to be complete in late 2022.
|
|
|
Ronald Reagan Corridor Planning Segment D (Williams Drive
and SH 195)
|
Project Limits and Length: 5 miles from Williams Drive to SH
195
Status: Status: The engineer, Rodriguez Transportation
Group, is working on planning for the roadway, which is anticipated to be
complete in late 2022.
|
|
|
Ronald Reagan Corridor Planning Segment E (SH 195 and IH-35)
|
Project Limits and Length: 6 miles from SH 195 to IH-35
Status: Status: The engineer, Pape Dawson, is working on
designing the planning for the roadway, which is anticipated to be complete in late 2022.
|
|
|