Project Name: Corridor C / SH 29 Bypass (P459)
Project Number/CSJ: CC 337-2-50 & CC 440-5-11 (0337-02-050 & 0440-05-011)
Limits: From Patriot Way to SH 29
Estimated Cost: $32M
Anticipated Letting Date: July 2022
Description: Construction of the first phase of a new facility linking Sam Houston Ave to SH 29 through a 2-lane roadway that overpasses SH 130
100% Plans – Subject to Change (Opens a pdf in a new window)
Corridor C/SH 29 Bypass Bid Form (Opens a pdf in a new window)
Project Name: FM 3349 at SH 79 (P332)
Project Number/CSJ: C 3486-1-8 ETC
Limits: FM 3349 from North of CR 404 to CR 395, etc.
Estimated Cost: $68M
Anticipated Letting Date: August 2022
Description: Construction of a four lane divided roadway consisting of grading, flex base, asphalt pavement, retaining walls, bridge structures, storm sewers, culverts, erosion control, signalization, illumination, signing, and pavement markings
100% Plan Vol I – Subject to Change (Opens a pdf in a new window)
100% Plan Vol II – Subject to Change (Opens a pdf in a new window)
100% Plan Vol III – Subject to Change (Opens a pdf in a new window)